PJM's Critical Issue Fast Path accelerated stakeholder process will inform a potential FERC filing on reliably serving large ...
Brandon Shores Unit 2 and both Wagner units can return to service once startup is complete; Brandon Shores Unit 1 is offline ...
Brandon Shores Unit 2 and both Wagner units can return to service once startup is complete; Brandon Shores Unit 1 is offline ...
BGE and PJM quickly restored service after Brandon Shores power plant shutdown, but Johns Hopkins expert says similar ...
The impacted substation has been repaired, according to Senate President Bill Ferguson, D-District 46. Ferguson said ...
Baltimore Gas & Electric (BGE) says its call to conserve electricity has ended, hours after a substation experienced an ...
A mass power outage in Central Maryland was avoided on Monday, following a transmission failure at a local Baltimore Gas and ...
About 4,000 in Howard County were without power for under a hour, BGE said Monday, pointing to an “unplanned” connection issue as the cause.
In an update on its website, BGE says that "a critical power plant [is] experiencing an unplanned disconnection from the BGE ...
Baltimore Gas & Electric briefly urged customers to conserve electricity Monday afternoon after an transmission facility failure forced a Maryland power plant offline, which could have caused ...
Exelon's Baltimore Gas & Electric said its call to conserve electricity has ended, hours after a substation experienced an unplanned disconnection from BGE's electric grid.